This paper circulates around the core theme of The following data were obtained from a project to design a new software package.Write a brief analysis of the status of the project at this time, including task level, project level, and critical path. together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.

Earned Value

The following data were obtained from a project to design a new software
package:

Activity

Duration

Predecessors

Budgeted
Cost

A

3
Days

$8,320

B

6
Days

$11,740

C

4
Days

A

$11,550

D

2
Days

C,
B

$7,850

E

3
Days

A

$10,750

F

2
Days

D,
E

$8,600

At the end of day 5, the status of the project is as follows:

Activity

%
Complete

Actual
Cost

A

100%

$7,200

B

50%

$6,370

C

25%

$8,250

D

0%

$0

E

80%

$8,560

F

0%

$0

(a) Calculate the Cost and Schedule Variances
and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E.

(b) Write a brief analysis of the status of the project at this time,
including task level, project level, and critical path.



International House, 12 Constance Street, London, United Kingdom,
E16 2DQ

Company # 11483120

Benefits You Get

  • Free Turnitin Report
  • Unlimited Revisions
  • Installment Plan
  • 24/7 Customer Support
  • Plagiarism Free Guarantee
  • 100% Confidentiality
  • 100% Satisfaction Guarantee
  • 100% Money-Back Guarantee
  • On-Time Delivery Guarantee
FLAT 50% OFF ON EVERY ORDER. Use "FLAT50" as your promo code during checkout