This paper circulates around the core theme of task time estimates for the modification of an assembly line at Jim Goodale’s Carbondale, together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.
task time estimates for the modification of an assembly line at Jim Goodale’s Carbondale,… 1 answer below » task time estimates for the modification of an assembly line at Jim Goodale’s Carbondale, Illinois, factory are as follows: a 6.0 – b 7.2 – c 5.0 a d 6.0 b,c e 4.5 b,c f 7.7 d g 4.0 e,f a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length? d) Draw a Gantt chart for the project. Nov 02 2015 01:40 AM