This paper circulates around the core theme of Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), the personnel in conflict and the number of people involved. (b) Note that operations cannot be split; what is the least cost method o together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.
Resource Allocation/Leveling
The following data were obtained from an in-house MIS project:
Activity
|
Duration
|
Predecessors
|
Personnel / Cost
|
A
|
3 Days
|
—
|
1 Systems Analyst/$260 day
|
B
|
6 Days
|
—
|
2 Programmers/$200 day each
|
C
|
3 Days
|
A
|
2 Programmers/$200 day each
|
D
|
3 Days
|
B
|
2 Hardware Specialists/$280 day each
|
E
|
3 Days
|
B
|
1 Hardware Specialist/$280 day
|
F
|
2 Days
|
C, D
|
1 Test Engineer/$300 day
|
Personnel Available
|
Quantity
|
Systems Analysts
|
1
|
Programmers
|
4
|
Hardware Specialists
|
2
|
Test Engineers
|
1
|
The software manufacturer has only the above
personnel available for the project. Additional personnel can be hired from
an agency at a 90% cost premium if needed.
(a) Identify any resource conflicts in the above project. State the
activities involved, the time frame of the conflict(s), the personnel in
conflict and the number of people involved.
(b) Note that operations cannot be split; what is the least cost method of
resolving the conflict(s), assuming the project duration must not be
extended? What additional cost, if any, will be incurred?