This paper circulates around the core theme of Given the data below, create two distinct active schedules together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.
Question
Dear Tutor, please solve this and provide explanations step by step. thank you
Given the data below, create two distinct active schedules, assuming more than one exists. Create two distinct non-delay schedules as well and compare all schedules on three common measures Completion time (C), Flow time (F), Tardiness (T).
Job
1
2
3
4
5
pi1
1
2
3
2
3
pi2
2
3
1
3
1
pi3
3
1
2
2
1
TC
1,2,3
1,3,2
3,2,1
2,1,3
3,2,1
Time due
10
10
6
12
8