This paper circulates around the core theme of find The crash cost per day per activity. Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity. together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.
Schedule Crashing
Using the network below and the additional information provided, find:
(a) The crash cost per day per activity.
(b) Which activities should be crashed to meet a project deadline of 13
days at minimum cost? State the number of days you will crash each
activity.
(c) What is the additional cost to crash the project?
Critical path = B-C-D = 15
.jpg”>
Activity
Normal
time
Normal
total cost
Crash
time
Crash
total cost
A
4
300
3
360
B
3
250
1
330
C
7
400
4
550
D
5
150
3
250