This paper circulates around the core theme of Calculate the Cost and Schedule Variances and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E. (b) Write a brief analysis of the status of the project at this time, including task level, project level, and critical path. together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.
The following data were obtained from a project to
design a new software package: Activity | Duration | Predecessors | Budgeted
Cost |
A | 3 Days | — | $8,320 |
B | 6 Days | — | $11,740 |
C | 4 Days | A | $11,550 |
D | 2 Days | C, B | $7,850 |
E | 3 Days | A | $10,750 |
F | 2 Days | D, E | $8,600 |
At the end of day 4, the status of the project is
as follows: Activity | % Complete | Actual Cost |
A | 100% | $7,200 |
B | 80% | $10,370 |
C | 25% | $8,250 |
D | 0% | $0 |
E | 80% | $8,560 |
F | 0% | $0 |
(a) Calculate the Cost and Schedule Variances and
Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E.
(b) Write a brief analysis of the status of the
project at this time, including task level, project level, and critical path.