This paper circulates around the core theme of Calculate Planned Order Releases for materials A-XXX, B-XXX, C-XXX, D-XXX, and E-XXX . Relevant data on independent requirements (forecast), BOM, and material master data are given below. together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.
Solve the Test Problem Manually
Calculate
Planned Order Releases for materials A-XXX, B-XXX, C-XXX, D-XXX, and E-XXX
. Relevant data on independent
requirements (forecast), BOM, and material master data are given below.
The
BOM for product A-XXX is shown below.
One unit of D-XXX and two units of E-XXX are assembled to make one unit
of C-XXX. Two units of C-XXX and one of
D-XXX are needed to make one subassembly of B-XXX. Four units of B-XXX are further assembled to
make one unit of the product A-XXX.
.0/msohtmlclip1/01/clip_image001.gif”>
Independent
Requirements (Forecast Demand) for Finished Product A-XXX
Period
|
Independent Requirements
|
Week 6/2014
|
15
|
Week 7/2014
|
20
|
Week 8/2014
|
30
|
Week 9/2014
|
25
|
Relevant
Material Master Data
Material
|
Lot Size
|
Lead Time
|
Procurement Type
|
Remarks
|
A-XXX
|
LFL
|
7 days
|
In-house Production
|
Finished Product
|
B-XXX
|
LFL
|
7 days
|
In-house Production
|
Semifinished Product
|
C-XXX
|
LFL
|
14days
|
In-house Production
|
Semifinished Product
|
D-XXX
|
Fixed Lot of 800
|
7 days
|
External Procurement
|
Raw Material
|
E-XXX
|
Fixed Lot of 1000
|
7 days
|
External Procurement
|
Raw Material |