This paper circulates around the core theme of The following data were obtained from a project to design a new software package.Calculate the Cost and Schedule Variances and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E. (b) Write a brief analysis of the status of the project at this time, i together with its essential aspects. It has been reviewed and purchased by the majority of students thus, this paper is rated 4.8 out of 5 points by the students. In addition to this, the price of this paper commences from £ 99. To get this paper written from the scratch, order this assignment now. 100% confidential, 100% plagiarism-free.
Earned Value
The following data were obtained from a project to design a new software
package:
Activity
|
Duration
|
Predecessors
|
Budgeted
Cost
|
A
|
3
Days
|
—
|
$8,320
|
B
|
6
Days
|
—
|
$11,740
|
C
|
4
Days
|
A
|
$11,550
|
D
|
2
Days
|
C,
B
|
$7,850
|
E
|
3
Days
|
A
|
$10,750
|
F
|
2
Days
|
D,
E
|
$8,600
|
At the end of day 5, the status of the project is as follows:
Activity
|
%
Complete
|
Actual
Cost
|
A
|
100%
|
$7,200
|
B
|
50%
|
$6,370
|
C
|
25%
|
$8,250
|
D
|
0%
|
$0
|
E
|
80%
|
$8,560
|
F
|
0%
|
$0
|
(a) Calculate the Cost and Schedule Variances
and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E.
(b) Write a brief analysis of the status of the project at this time,
including task level, project level, and critical path.