Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity.

Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity.

Using the network below and the additional information provided, find:

(a) The crash cost per day per activity.

(b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity.

(c) What is the additional cost to crash the project?

Critical path = B-C-D = 14

Activity | Normal time | Normal total cost | Crash time | Crash total cost |

A | 5 | 300 | 3 | 380 |

B | 3 | 250 | 1 | 330 |

C | 6 | 400 | 4 | 700 |

D | 5 | 150 | 3 | 250 |

|