Using the network below and the additional information provided, find:  (a) The crash cost per day per activity. (b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each ac

Using the network below and the additional information provided, find: (a) The crash cost per day per activity. (b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each ac

Schedule Crashing

Using the network below and the additional information provided, find:

(a) The crash cost per day per activity.
(b) Which activities should be crashed to meet a project deadline of 13
days at minimum cost? State the number of days you will crash each
activity.
(c) What is the additional cost to crash the project?

Critical path = B-C-D = 15

Keller PROJ 592 Final Exam Questions.jpg”>

Activity

Normal
time

Normal
total cost

Crash
time

Crash
total cost

A

4

300

3

360

B

3

250

1

330

C

7

400

4

550

D

5

150

3

250