Project 1: Determine the design flow for the transmission pipes RA, AB and BC shown on the figure below.

Project 1: Determine the design flow for the transmission pipes RA, AB and BC shown on the figure below. Also determine the storage volume required at the storage Reservoir.   
Design Data: 1. Pump P1 is 3 m below the reservoir water level. 2. Water demand 500 L/c/d 3. Pipe roughness height = 1 mm 4. Maximum day factor = 1.8 5. Maximum hour factor = 3.25 6. Assume  Pipe diameter  
 Elevation Population to serve 
Length of Transmission pipe 
Fire flow demand 
Minimum pressure required Reservoir Level  100.00 m     Distribution Point  A 120.00 m 50,000 R to A = 5 Km 15000 L/min 600 kPa Distribution Point B 140.00 m 20,000 A to B = 7 Km 10,000 L/min 550 kPa Distribution Point C 170.00 m 30,000 B to C = 10 Km 12,000 L/min 480 kPa  


Price: £ 24

100% Plagiarism Free & Custom Written, Tailored to your instructions