find The crash cost per day per activity. Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity.

find The crash cost per day per activity. Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity.

Schedule Crashing

Using the network below and the additional information provided, find:

(a) The crash cost per day per activity.
(b) Which activities should be crashed to meet a project deadline of 13
days at minimum cost? State the number of days you will crash each
activity.
(c) What is the additional cost to crash the project?

Critical path = B-C-D = 15

Keller PROJ 592 Final Exam Questions.jpg”>

Activity

Normal
time

Normal
total cost

Crash
time

Crash
total cost

A

4

300

3

360

B

3

250

1

330

C

7

400

4

550

D

5

150

3

250