find The crash cost per day per activity.  (b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity.  (c) What is the additional cost to crash the project?

find The crash cost per day per activity. (b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? State the number of days you will crash each activity. (c) What is the additional cost to crash the project?

Question 1. | Question : | (TCO C)
Schedule Crashing

Using the network below and the additional
information provided, find:

(a) The crash cost per day per activity.

(b) Which activities should be crashed to meet a
project deadline of 13 days at minimum cost? State the number of days you will
crash each activity.

(c) What is the additional cost to crash the
project?

Critical path = B-C-D = 14

Activity | Normal time | Normal total cost |
Crash time | Crash total cost |

A | 5 | 300 | 3 | 380 |

B | 3 | 250 | 1 | 330 |

C | 6 | 400 | 4 | 700 |

D | 5 | 150 | 3 | 250 |