Compute the NPV for Project Y and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.

Compute the NPV for Project Y and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.

Compute the NPV for Project Y and
accept or reject the project with the cash flows shown below if the appropriate
cost of capital is 10 percent.

TIME: 012345 CASH FLOW: -1000 -2,000 3,000 0 1,000
2,500