Earned Value

The following data were obtained from a project to design a new software
package:

Activity

Duration

Predecessors

Budgeted
Cost

A

3
Days

$8,320

B

6
Days

$11,740

C

4
Days

A

$11,550

D

2
Days

C,
B

$7,850

E

3
Days

A

$10,750

F

2
Days

D,
E

$8,600

At the end of day 5, the status of the project is as follows:

Activity

%
Complete

Actual
Cost

A

100%

$7,200

B

50%

$6,370

C

25%

$8,250

D

0%

$0

E

80%

$8,560

F

0%

$0

(a) Calculate the Cost and Schedule Variances
and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E.

(b) Write a brief analysis of the status of the project at this time,
including task level, project level, and critical path.