Calculate the Cost and Schedule Variances and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E.  (b) Write a brief analysis of the status of the project at this time, including task level, project level, and critical path.

Calculate the Cost and Schedule Variances and Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E. (b) Write a brief analysis of the status of the project at this time, including task level, project level, and critical path.

The following data were obtained from a project to
design a new software package: Activity | Duration | Predecessors | Budgeted
Cost |

A | 3 Days | — | $8,320 |

B | 6 Days | — | $11,740 |

C | 4 Days | A | $11,550 |

D | 2 Days | C, B | $7,850 |

E | 3 Days | A | $10,750 |

F | 2 Days | D, E | $8,600 |

At the end of day 4, the status of the project is
as follows: Activity | % Complete | Actual Cost |

A | 100% | $7,200 |

B | 80% | $10,370 |

C | 25% | $8,250 |

D | 0% | $0 |

E | 80% | $8,560 |

F | 0% | $0 |

(a) Calculate the Cost and Schedule Variances and
Indexes (CV, SV, CPI, SPI) for tasks A, B, C, D, and E.

(b) Write a brief analysis of the status of the
project at this time, including task level, project level, and critical path.