Calculate Planned Order Releases for materials A-XXX, B-XXX, C-XXX, D-XXX, and E-XXX . Relevant data on independent requirements (forecast), BOM, and material master data are given below.

Calculate Planned Order Releases for materials A-XXX, B-XXX, C-XXX, D-XXX, and E-XXX . Relevant data on independent requirements (forecast), BOM, and material master data are given below.

Solve the Test Problem Manually

Calculate
Planned Order Releases for materials A-XXX, B-XXX, C-XXX, D-XXX, and E-XXX
. Relevant data on independent
requirements (forecast), BOM, and material master data are given below.

The
BOM for product A-XXX is shown below.
One unit of D-XXX and two units of E-XXX are assembled to make one unit
of C-XXX. Two units of C-XXX and one of
D-XXX are needed to make one subassembly of B-XXX. Four units of B-XXX are further assembled to
make one unit of the product A-XXX.

Production Planning and Control.0/msohtmlclip1/01/clip_image001.gif”>

Independent
Requirements (Forecast Demand) for Finished Product A-XXX

Period

Independent Requirements

Week 6/2014

15

Week 7/2014

20

Week 8/2014

30

Week 9/2014

25

Relevant
Material Master Data

Material

Lot Size

Lead Time

Procurement Type

Remarks

A-XXX

LFL

7 days

In-house Production

Finished Product

B-XXX

LFL

7 days

In-house Production

Semifinished Product

C-XXX

LFL

14days

In-house Production

Semifinished Product

D-XXX

Fixed Lot of 800

7 days

External Procurement

Raw Material

E-XXX

Fixed Lot of 1000

7 days

External Procurement

Raw Material


Price: £ 45